Lagos-Calabar Coastal Highway 70% completed, January 2026 delivery expected – Umahi

457

 

Caption:Minister of Works, Sen. Dave Umahi (second from left), during inspection of Lagos-Calabar Coastal Highway project on Wednesday

The Lagos-Calabar Coastal Highway construction will be completed in January 2026, the Minister of Works, Sen. Dave Umahi, has said.

Umahi made the disclosure during an inspection tour of the highway on Wednesday.

“We came to review the project with the financial promoters – Dutch Bank and Development Bank of Southern Africa,” he said.

 

 

He said it was projected that 20km of the road (from Ahmadu Bello Way in Lagos) would have been completed by May.

“We are going to surpass the 20km from this site,” he said.

Umahi said that more than 70 per cent of the entire project had been done.

“Let me state that this project is over 70 per cent done, and the contractor has not got funds up to 70 per cent.

“That is why I call them people that have set their minds towards nation-building rather than making money.”

According to him, along the corridor, there are some lands that have been acquired for tourism, industries, factories and housing estates.

“ These are the road architecture that you are going to receive on this highway.

“I assure you that by January next year, God willing, we have this road completed,” the minister said.

He said that the financial promoters of the highway were satisfied with the work progress, quality, method statement, and every other thing about the project.

He praised the contractor handling the project, Hitech Construction Company, for efforts.

“The road is exceptionally technically well-designed.

“The concrete thickness is designed for 275 millimetres but what they are doing is 280 millimetres.

“ I commend also the department in charge of this project – the Department of Bridge and Roads, and, of course, the controller of works in Lagos,” he said.

Umahi said that the greatest worry he could have would be motorists joining the highway ‘from their houses’.

Also Read:Akute-Olambe-Agbado Road:Now that the Rain has come

Lagos to start works on 68km Green line rail project this year

FG flags off C’River section of 750km Lagos/ Calabar highway

 

 

“It is going to be a very serious issue; so, we have to design a barrier.

“ I know that you are putting a retaining wall but you have not incorporated a retaining wall all through.”

He said that, as a superhighway, it would be expected that motorists would join it at flyovers and interchanges to avoid gridlock. (NAN)

Kindly support the growth of journalism in Nigeria
To Receive FREE Newdawn News Online on your phone, text your number to +2348104502834

TAG

Reactions to stories published can be sent to us at info@newdawnngr.com


Leave a Reply

Your email address will not be published. Required fields are marked *